St. Andrews Tank Upgrades
Location
Cambridge, ONClient
The Regional Municipality of Waterloo Status: In Progress Consultant: GEI ConsultantsThe St. Andrews Tank Upgrade can be broken out into 5 main activities. Including Site Preparation, New Tank, Valve Chamber, Existing Pumping Station Upgrades, and Commissioning.
KCL is working with Greatario to build a new water tank on site. KCL will work to build the tank foundation and walls and pass off the remaining works to Greatario for the tank build.
KCL will begin on the Valve Chamber upgrades which will lead to electrical upgrades on the interior of the existing building.